Project Engineering & Project Controls Calculators

Practical construction calculators for project engineers, planners, quantity surveyors, procurement teams and MEP/piping professionals. Start with simple project inputs and progress into productivity, earned value, forecasting, procurement and commercial controls.

01 · PLANNING

Project Duration & Working Days Calculator

Convert calendar dates into practical working days after considering the selected weekly work pattern.

Step 1 — Select dates and workweek

Calendar Days—
Working Days—
Non-working Days—
Working days are counted inclusively. Public holidays are not deducted in this version.
02 · RESOURCE PLANNING

Manpower, Productivity & Duration Calculator

Useful for piping, welding, fabrication, civil, MEP and repetitive construction activities.

Step 1 — Define the work

Crew Daily Output—
Duration with Current Crew—
Workers for Target—
Total Worker-Days—
Duration = Quantity ÷ (Workers × Productivity). Required workers = Quantity ÷ (Target days × Productivity).
03 · PROJECT CONTROLS

Earned Value Management — Basic to Advanced

Begin with familiar percentages, then automatically obtain PV, EV, schedule/cost indices and final project forecasts.

Step 1 — Simple project status

Step 2 — Earned value & variance

Planned Value (PV)—
Earned Value (EV)—
Schedule Variance (SV)—
Cost Variance (CV)—

Step 3 — Performance indices

SPI = EV / PV—
CPI = EV / AC—
Schedule Status—
Cost Status—

Step 4 — Forecast at completion

EAC (CPI basis)—
ETC—
VAC—
TCPI to BAC—
PV = BAC × planned %. EV = BAC × actual physical %. SV = EV − PV. CV = EV − AC. SPI = EV/PV. CPI = EV/AC. EAC = BAC/CPI. ETC = EAC − AC. VAC = BAC − EAC. TCPI = (BAC − EV)/(BAC − AC).
04 · RECOVERY PLANNING

Project Delay Recovery Calculator

Estimate the output and manpower required to complete remaining work within a recovery period.

Remaining Quantity—
Required Daily Output—
Required Workers—
Additional Workers—
05 · PIPING CONSTRUCTION

Piping & Welding Progress Planner

Convert pipe joints into diameter-inch workload and estimate welding duration, manpower and NDT quantities.

Step 1 — Welding workload

Total Dia-Inch—
Remaining Joints—
Estimated Remaining Days—
NDT Joints—
Simplified diameter-inch = nominal pipe diameter (in.) × number of circumferential butt-weld joints. Actual productivity depends on thickness, material, welding process, access, position, WPS, fit-up and inspection requirements.
06 · PROCUREMENT

Latest PO / Material Order Date Calculator

Work backward from the required-on-site date through shipping, manufacturing, approvals and procurement processing.

Total Procurement Lead Time—
Latest Procurement Start—
07 · MATERIAL CONTROL

Safety Stock & Reorder Point Calculator

Estimate stock required to cover normal consumption, procurement lead time and a selected safety allowance.

Lead-Time Demand—
Safety Stock—
Reorder Point—
Current Stock Coverage—
08 · VENDOR EVALUATION

Weighted Supplier Evaluation Calculator

Compare a supplier using technical, commercial, delivery and quality criteria. Scores are entered from 0 to 100.

Overall Weighted Score—
Indicative Rating—
Weights should be adjusted to suit the project's approved vendor evaluation procedure.
09 · ESTIMATION

Construction Unit Rate & Selling Price Calculator

Build a unit rate from labour, material, equipment and subcontract costs, then add overhead, contingency and profit.

Direct Cost—
Cost incl. OH & Contingency—
Selling Price—
Selling Unit Rate—
10 · COMMERCIAL CONTROL

Progress Billing / IPC Calculator

Estimate a simplified interim payment from contract value and certified progress after retention, advance recovery and previous certificates.

Gross Work Value—
Retention—
Current Net Before VAT—
Current Amount incl. VAT—
This is a simplified planning calculator. Actual IPC valuation must follow the contract's rules for retention, advance recovery, materials on site, variations, deductions and tax.
BONUS · PROJECT CONTROLS

Simple S-Curve Progress Visualizer

Enter cumulative planned and actual progress values to visualize schedule movement without loading an external chart library.

For formal project controls, monthly or weekly time-phased budget data should be used rather than assuming progress percentages alone.

Need Project-Specific Engineering Support?

For piping, district cooling, MEP, construction planning, estimation or project engineering assistance, contact the PSEMIC engineering team.

Get Expert Advice from PSEMIC

Engineering note: These calculators are preliminary planning and estimation aids. Verify results against approved drawings, specifications, contracts, codes, manufacturer data, WPS/PQR, project procedures and site conditions before execution.